  • ITD activity aimed at the most efficient use of the territories. It includes preparation and approval of planning documentation for residential, industrial, public-business construction and development of communal, transport and social infrastructures

ITD Scheme

  • 1
    Make an agreement

    Make an agreement between rightholders (for two and more) about segregation of dutes connected with ITD

  • 2
    Project development

    Development of area planning design, area demarcation plan and ITD draft by rightholders themselves

  • 3
    Documents verification

    Documents verification by Moscow Government in accordance to Russian Laws

  • 4
    Progect confirmation

    Documents confirmation by Moscow Government

  • 5
    Signing a contract

    Signing a ITD contract by Moscow Government

  • 6
    Signing a contract

    Signing a ITD contract by rightholders

  • 7
    Project implementation

    ITD project realization in accordance with sighning contracts

  • 1
    Decision

    Making a desicion about ITD at the instance of Moscow Government

    • Capital construction objects in critical conditions
    • Demolition and reconstruction of objects,included in targeted investment program
    • Characteristics don't compare land use and development rules
    • Unauthorized construction
  • 2
    ITD suggestion

    Making ITD suggestion to rightholders and declaration of ITD

  • 3
    Waiting for documents from rightholders

    Conclusion of an agreement between rightholders, formulation of the documents, sending the documents to Moscow Government in case of acceptance

  • 4
    Taking a decision

    Taking a decision by Moscow Government about auction for the right to ITD, not earlier than 6 months after completing step 1 and upon condition the failure of step 3

  • 5
    An auction

    Moscow Government conducts an auction for the right of ITD

  • 6
    Signing a contract

    Signing ITD contract with the auction winner 

  • 7
    Project development

    Formulation of area planning design and area demarcation plan by assigned party

  • 8
    Approval

    Moscow Government approve the documents

  • 9
    Withdrawal at the request

    Withdrawal of land plots and capital construction objects

  • 10
    Project implementation

    ITD project implementation according to the contract and other documents.

Laws and regilations

Name Date
1 Federal law from 03.07.2016 N 373-ФЗ May 28, 2019 Download
2 Integrated territorial development of production zone №28а «Biryulyovo» September 19, 2017 Download
3 Integrated territorial development of production zone №46 «Korovino» September 19, 2017 Download
4 Integrated territorial development of production zone №44 «Bratcevo» March 16, 2018 Download
5 Integrated territorial development of production zone №41 «Oktyabrskoye pole» May 28, 2019 Download
6 Moscow Government Resolution №215-PP April 24, 2017 Download
Name Date
1 Department of investment and industrial policy of Moscow 01.12.2019 Link
2 Town Planning Code of Russia (as reworded by Federal Law 02.08.2019 № 283-ФЗ) 01.12.2019 Link
3 Land Code of Russia (art. 39.6 и VII capter) 01.12.2019 Link
4 Moscow Government Resolution 24.04.2017 N 215-ПП (re. from 19.02.2019) 01.12.2019 Link

null

null

null

Send a request
for site selection

Send message

Send message